go to top scroll for more

Projects


Projects: Projects for Investigator
Reference Number NIA_SGN0051
Title Olympic Rings for RIIO
Status Completed
Energy Categories Fossil Fuels: Oil Gas and Coal(Oil and Gas, Refining, transport and storage of oil and gas) 100%;
Research Types Applied Research and Development 100%
Science and Technology Fields PHYSICAL SCIENCES AND MATHEMATICS (Metallurgy and Materials) 50%;
ENGINEERING AND TECHNOLOGY (Mechanical, Aeronautical and Manufacturing Engineering) 50%;
UKERC Cross Cutting Characterisation Not Cross-cutting 100%
Principal Investigator Project Contact
No email address given
SGN
Award Type Network Innovation Allowance
Funding Source Ofgem
Start Date 01 September 2014
End Date 01 January 2017
Duration 30 months
Total Grant Value £80,000
Industrial Sectors Technical Consultancy
Region South East
Programme Network Innovation Allowance
 
Investigators Principal Investigator Project Contact , SGN (100.000%)
Web Site http://www.smarternetworks.org/project/NIA_SGN0051
Objectives The objectives of this project are to: Produce a conceptual detailed design solution to meet SGN and Industry standards. Conceptual detailed design of reinstatement process Off site field trials to prove conceptual design compatibility Technical review of impact of conceptual process across spectrum of road classifications Gap analysis On site field trials to prove process including testing and monitoring process Production of report detailing process and testing results. The success criteria for this project are to trial and test the method against the traditional methods currently used to compare its performance in terms of: Provide a safe, efficient and cost effective solution. Demonstrate the effectiveness of the technique versus existing excavationsDemonstrate the effect of multiple cores on carriageway integrityProvide test data to uphold conclusionsIncrease in productivity.
Abstract Scotia Gas Networks (SGN) is currently undertaking a programme of work to replace existing cast iron mains with new PE mains. This work is undertaken in tandem with conventional abandonment works which allows the metallic mains to be decommissioned. Both of these activities currently require large excavation works to be undertaken on the carriageway causing disruption to traffic flows for extended time periods. These excavations also impact on the environment with the disposal of excavated material and the import of either virgin or recycled backfill material. Under the previous IFI initiative, SGN undertook a project to evaluate Core &Vac technology to assist in minimizing excavation sizes when carrying out joint repairs on metallic mains. This project will look at extending the use of core and vac technology and techniques to allow larger excavations to be carried out and backfilled using multiple coring. The use of core and vac is currently limited due to the size restrictions and the tooling available to operate within the limited space of a core excavation (600mm diameter). This means a large number of operations still involve large, time consuming excavations ranging from 2 - 4 metres in length depending on pipeconfiguration and the associated delay in reinstatement. This project would develop a technique to allow the extension of core and vac technology to include multiple cores , thereby allowing the use of conventional tooling and equipment to operate in conjunction with the core and vac technology. The benefits of this system when compared with conventional drilling and bag off equipment are: Reduction in volume of excavationMinimise our works footprintQuickly reinstate the majority of the excavation worksReduces time both excavating and reinstatingReduces costs minimise excavation size and, where core and vac is used, cores can be used as final reinstatementNote : Project Documents may be available via the ENA Smarter Networks Portal using the Website link above
Publications (none)
Final Report (none)
Added to Database 17/09/18